Composite photovoltaic, energy storage, diesel and public grid resources to support grid-connection, island-free, black-starting and restoration of grid-connected systems for critical, critical and general loads.
DEMO PROJECT
Two sets of 5MWh DC Block.
Supporting Microgrid's connection, island and black.
10.128 MWh Microgrid Project = Key Loads for Large Businesses and Parks
Networking
On the island.
Black Start
Critical load security
DEMO PROJECT
TC-DEMO-PROJ-MG-10128
Total battery capacity
10.128 MWh
PCS Total Power
2.5 MW
On-site acceptance status
SAT PASSED
Project overview Multi-source Assets & Critical Load Priority
Structure of the System Single-line & Control Architecture
DC Block A
5.064 MWh
DC 1,500V
PCS-1
1.25 MW
AC 35 kV
Microgrid controller
Microgrid Controller
Protection & SCADA
Protection & SCADA
Photovolt/ grid/ generator
Optical Array
PV 2.8 MW
Municipal electricity
Utility Grid
Stand-by generators
Generator 2.0 MW
DC Block B
5.064 MWh
DC 1,500V
Critical load priority
P1
Control.
400 kW
P2
Production line
500 kW
P3
Office building
300 kW
P4
Public Load
200 kW
Run State Evolution State Transition Timeline
Load removal order
1
P4 Public facilities
200 kW
2
P3 Office building
300 kW
3
P2 Production line
500 kW
Black Start Restore
1
PCS Construction Pressure
t + 8 min
2
Restoring critical load
t + 12 min
3
P2 → P3 → P4 Gradual recovery
15–25 min
Communications and autonomous control Resilience & Autonomous Control
SCADA / EMS
Microgrid controller
PCS controller
BMS System
×
Local control
- Frequency / voltage control
- Power distribution
- Protect Actions
- Black Start Logic
- Load priority restored.
Time Sync
PTP / NTP < 1 msPlant acceptance and site integration FAT & Field Integration
FAT Test
PCS Function Test
BMS & Battery Cluster Test
Protect and Link
Black Start Logic
Communications interface
Fault injection test.
Field integration
Equipment installation
System Integration
Electricity and relay inputs
On-site black-start test.
Operation tests on the island
Network restoration test
On-site acceptance and inspection results SAT Transfer & Punch-list
Test scene
18
Item
Critical load security
100%
The island phase
Frequency deviation
±0.08 Hz
On the island.
Pressure deviation
±1.2%
35kV bus
List of issues
0
Closed
Control room live. Control Room Evidence
Event Record
00:00:00
Networking
00:02:13
Power grid failure.
00:08:24
Island stability
00:18:37
Blackstart complete.
00:32:11
Reconnect
Operational strategy and delivery Operations & Delivery
Run Policy
Role Permissions
MA
Administrator Admin
OP
Operation Engineer
VW
Watchman, Viewer.
Delivery documents
Line Chart
Single-line
Single-line
FAT Report
SAT report
O&M Manual
Delivery completed
Complete system testing, on-site acceptance, running Training, power configuration and transfer of engineering information, and the system is officially in the long run.