Integrated lithium battery energy storage solutions
AS-IS Existing System 9.90MWh Shipment 2019
40ft Containerized BESS × 9
TO-BE Capability Component 2.61 MWh Add Add Battery Box x 12
0.261 MWh / cabinet
Switching field
CUTOVER ZONE
Isolated Border / ISOLATION BOUNDAY
SYSTEM RETROFIT & EXPANSION System Retrofit & Express

In the already established system boundaries,
Revertable, verifiable
Rehabilitation and expansion

Minimal shutdown risk control interface compatibility verifiable delivery
Evidence cockpit & nbsp; EVIDENCE COCBIT

TC-DEMO-PROJ-RETRO-2610

Type of project System Retrofit & Expansion
Original system capacity 9.90MWh
Add Capacity 2.61MWh
Switch Window 4.0 hours
Implementation time 2025-05-12
Existing system (maintained) EXISTING PATHS
Change / Add Range CHANGED / NEW SCOPE
ISOLATION ONLY
Toggle field CUTOVER ZONE

1 Survey of the status of existing systems AS-IS

List of assets (partial)
Battery systems 40ft container x 9
PCS 1.25MW × 6
EMS TC-EMS-3000 V2.3.1
BMS TC-BMS-3000 V2.1.8
Pressure system 10kV ringboard x 11
Cooling system Liquid chiller team x 9
FIRE FIGHTING SYSTEM Gas extinguisher + smoke + temperature
Interfaces and protocols
BMS-EMS Modbus TCP
EMS-PCS IEC 61850 MMS
EMS-SCADA OPC UA
Time Sync NTP / GPS
Capacity and operation
Scale Capacity 9.90MWh
Available capacity 9.21MWh(SOH 93.0%)
Original PCS Power 7.50MW
Maximum charge power 7.50MW
Maximum discharge power 7.50MW

Operational limitations and risks

  • PCS 08 Run temperature rises high
  • Some old BMS points are inconsistent with current standards
  • There is a historical compatibility problem with inter-chamber communications
  • Switch window requires less than 4 hours

2 Target structure TO-BE

Add Capacity
Add Batteries 12 (0.261 MWh / cabinet)
Add Capacity 2.61MWh
Total expanded capacity 12.51MWh
Availability after expansion 11.60 MWh (target 94% ≥)
Structure and interface adjustments
PCS Add 1.25 MW x 2
EMS Maintain the main system and expand the new equipment model
BMS Add BMS Subnet Access
Pressure system Add Feed 2 Back
Cooling system Add liquid chiller team x 2
FIRE FIGHTING SYSTEM Add separate partitions and access to the original fire system
Available capacity 10.00MW / 12.51MWh

3 Multi-professional differences and impact matrix DIFFERENCE / IMPACT MATRIX

Professional field Variance/change of content Scope of impact Risk level Mitigation Validation of evidence
Electrical Add PCS, Outboard, Direct Flow Electrical single, protective, metrology High Load calibration, protection and containment. Testing reports, consolidation of records
Communications Add BMS/ PCS access, fibre-optic expansion Networking, bandwidth, redundancy High Network segment, QoS, redundant links COMMUNITY TESTING, DISTRIBUTION RATE REPORT
Control EMS Point Table Extension, Control Strategy Adjustment Dispatch, data, and interlocking High Strategic simulation, alignment and event review Policy evaluation, simulation data
Thermal management New liquid chiller, pipe extension. Dispersive capacity, flow balance Low CDF review, flow balance test Flow / Temperature Test Record
Fire New fire-fighting partitions and associated interfaces Detect, connect, link. High Fire protection design, connection test Linked test logs
Wall / Built New base, quarantine fence. Heavy bearing, passage, fire-proof partition Medium Review carried out, fire zonation adjusted Structural acceptance, blocking records
Interface Networking point capacity change, communication fit Networking, protection, movement High Short-circuit calculations, protection review Computation books, system reports
File/ Data Charts, asset desk accounts, table updates Full process document consistency Low Version control, cross-read List of documents, proofreading reports

4 Switch Project Design CUTOVER ENGINEERING

Stop window 4.0 hours (02:00-06:00)
Switch power. 400kVA emergency generator x 1
Work permit work ticket x 12, operating ticket x 18
Isolation Point DC 16, AC 12
Switch order The original system drops and separates.
Keep it steady. HP-1 / HP-2 / HP-3 / HP-4
Return trigger condition Either key authentication failed/ protection anomaly/ communication interrupted
Backback recovery time 2.0 hours

5 Compatibility of old and new systems COMPATIBILITY & INTEGRATION

BMS Protocol Modbus TCP (reserved)
EMS-PCS Protocol IEC 61,850 MMS (maintenance)
Address/ Point Map Add a new tabulation and maintain the original name system
Solidware Version BMS V2.1.9 / PCS V1.6.4 / EMS V2.3.2
Control of command behaviour Power setting, limit flow, locking, repositioning logic.
Reports and incidents Rating mapping, plant uniform display
Data continuity Keep historical data and continuous mapping of new data
Compatible conclusions Toggle can be implemented by compatibility verification

6 Phased installation Online production environment

1. Field survey and positioning

Border confirmation, route review, quarantine range marking.

2. Land-building and infrastructure preparations

Basic construction, pre-burial, load and size review.

3. Placing and installation of equipment

Battery cabinets, PCS and electrical distribution equipment are in place in stages.

4. High and low pressure and pre-positioning of communications

Pre-enforcing cable and network work was completed prior to the shutdown.

5. Original system validation

Maintain existing systems and complete pre-interchange baseline confirmation.

6. Sub-sector production and operation

Sectors are online and segmented to reduce overall downside risk.

7 Switch Timeline CUTOVER TIMELINE

T-30min Pre-check

00:00–02:00

  • System stabilization check
  • Protect Parameter Confirm
  • Communication link confirmed.
  • Operator / Tool Ready
  • HP-1 precheck completed
Evidence: System List & Signature
T-30min isolation

02:00–02:30

  • We'll stop in order.
  • DC isolation at 16 points
  • Communication isolation 12 places
  • Lock card
  • HP-2 Segregation confirmed
Evidence: Segregation forms
Switch SWITCH

02:30–03:30

  • New Device Access
  • Cable / fibre optic connection
  • Organisation
  • Control interface check
  • HP-3 Switch complete
Evidence: Construction records & photographs
T+00min Authentication

03:30–04:30

  • Electron sequence execution
  • Communications coordination
  • Function and Protection Test
  • Data consistency checks
  • HP-4 validation complete
Evidence: Test report
T+60min RELEASE / ROLLBACK

04:30–06:00

  • Project Run Load
  • Performance baseline match
  • No anomalies in publishing run
  • Unusual.
  • Restore to AS-IS Status
Evidence: Run records / Back logs

8 Pre- and post-reform performance comparisons BASELINE VS POST-RETROFIT

Indicators Pre-reform (AS-IS) Modified (TO-BE) Change
Scale Capacity 9.90MWh 12.51MWh +2.61MWh
Available / SOH 9.21MWh / 93.0% 11.80MWh / 94.3% +2.59MWh
Maximum charge power 7.50MW 10.00MW +2.50MW
Maximum discharge power 7.50MW 10.00MW +2.50MW
System efficiency 93.1% 93.4% +0.3pp
System availability (30 days) 99.32% 99.41% +0.09pp
Average number of daily cycles 1.42 1.48 +0.06
Temperature differential (battery module) ΔT ≤ 5.2°C ΔT ≤ 4.1°C Optimization
  • Post-embracing system rated capacity increased to 12.51 MWh.
  • The original system maintains a business logic and the new system is configured compatible.
  • Switch to perform performance, heat management, efficiency and power response validation.
Power curve (typical day)
Efficiency Curve
Temperature Distribution
Volume comparison

9 Project evidence TC-DEMO-PROJ-RETRO-2610

AS-IS Total plane (before modification)

TO-BE Total plane (modified)

Capability completed (field scene)

Operational evidence (platform screenshot)

Capacity 12.51MWh
Power 10.00MW
SOC 53.7%
Run Status &Normal
Alarm 0

10 Delivery and handover DOCUMENTATION & HANDOVER

CR
Change records
  • MOC List
  • Change impact assessment
  • Approval records
DWG
Maps and Documents
  • Red line drawings
  • Completed drawings
  • Interface / Wire
ASSET
Asset desk accounts
  • Device table update
  • Serial number/ version
  • List of spare parts
CFG
Points and Parameters
  • Table V1.2
  • Parameter Matrix
  • List of full values
TEST
Test report
  • Plant testing
  • Field tests
  • SAT report
TRN
Training and Transfer
  • Transport
  • Operations manual
  • Transfer of confirmation forms
Project plan and implementation report Risk list and control Switch Record Test Record Performance baseline report Report on capacity statistics List of spare parts Transport Recommendations
R

Discuss retrofit and expansion boundaries

Status inventory, retrofit assessment, switching programme, risk assessment, system validation and safe return to efficient operation.